Conduit Fill Calculator

Add up the cross-sectional area of every conductor and pick the smallest conduit whose allowed fill (53%, 31%, or 40% by wire count) is at least that big.

Estimate only. Results are estimates. Verify against the applicable code and manufacturer specifications before relying on them for safety-related work.

Conduit type
in
Optional. Use the major diameter for oval cables such as NM.
Minimum conduit trade size
1/2in
Total conductor area0.0399 in²
Fill limit applied40 %
Fill in that conduit13.1 %

Many specifications set 3/4 in as the smallest conduit. Fill only tells you the code minimum, not the easiest pull.

Count equipment grounding conductors too: Chapter 9 Note 3 requires them in the fill.

Show the math

3 × 0.0133 in² (12 AWG THHN/THWN) = 0.0399 in²
Total conductor area = 0.0399 in² (3 conductors, 40% fill limit)
Smallest EMT whose internal area × 40% covers 0.0399 in² = 1/2 in

Rounded the same way as the result above.

How it works

NEC Chapter 9 limits how much of a conduit's cross-section wires may fill so they can be pulled and can shed heat. One wire may fill 53%, two wires 31%, and three or more wires 40%. A short nipple (24 inches or less) may go to 60%.

Look up each conductor's area (Table 5), multiply by how many you have, and add them up, including the equipment ground. Then find the smallest conduit whose internal area (Table 4) times the fill percentage is at least that total. A multiconductor cable counts as a single conductor at its overall diameter.

Total area = Σ (conductor area × quantity) Allowed area = conduit internal area × fill limit (53% one wire, 31% two, 40% over two, 60% nipple) Pick the smallest trade size where total area ≤ allowed area

Worked example

Three 10 AWG THHN conductors in EMT (the published answer is 1/2 inch for the wires alone):

  1. 3 × 0.0211 in² (10 AWG THHN/THWN) = 0.0633 in²
  2. Total conductor area = 0.0633 in² (3 conductors, 40% fill limit)
  3. Smallest EMT whose internal area × 40% covers 0.0633 in² = 1/2 in
InputValue
Conduit typeEMT
InstallationConduit run (Chapter 9 Table 1)
Conductor size and type, group 110 AWG THHN/THWN
Quantity, group 13
Conductor size and type, group 214 AWG THHN/THWN
Quantity, group 20
Conductor size and type, group 314 AWG THHN/THWN
Quantity, group 30
Conductor size and type, group 414 AWG THHN/THWN
Quantity, group 40
Multiconductor cable outside diameter (cable is counted at its major diameter)0.39 in
Number of multiconductor cables0
ResultValue
Minimum conduit trade size1/2 in
Total conductor area0.0633 in²
Fill limit applied40 %
Fill in that conduit20.8 %

Assumptions and limits

  • Areas are the approximate conductor areas in Chapter 9 Table 5 for THHN/THWN and XHHW, and the conduit areas in Table 4. THHW and compact conductors are not included.
  • When every conductor has the same area, Note 7 lets a count with a remainder of 0.8 or more round up. This tool applies that rule.
  • Includes only the areas you enter. Do not forget the equipment grounding conductor.
  • Conduit bodies, bends, and pull length do not change the fill limit, but they change how hard the pull is. Check the adopted NEC edition and any local amendments.

Common questions

How many wires can I put in a 1/2 inch EMT?

Using the 40% limit, 1/2 inch EMT holds up to twelve 14 AWG THHN, nine 12 AWG THHN, five 10 AWG THHN, three 8 AWG THHN, or two 6 AWG THHN conductors, counting the ground.

Why is the fill limit lower for two wires?

Two conductors of a size that fills 40% or more of a conduit can jam against each other, so Chapter 9 Table 1 holds two-wire fill to 31%.

Do I count the ground wire?

Yes. Chapter 9 Note 3 says equipment grounding conductors and bonding jumpers count in conduit fill.

What is the 60% nipple rule?

A conduit nipple that is 24 inches or less between boxes or cabinets may be filled to 60% instead of 40% (Chapter 9 Note 4).

Sources

  • NEC (NFPA 70) Chapter 9: Table 1 (percent of conduit fill), Table 4 (conduit dimensions), Table 5 (conductor dimensions), Notes 3, 4, 5, 7 and 9.
  • Table values transcribed from PDHonline Course E276, Conduit Fill Calculations, which reproduces those tables. Confirm against the NEC edition adopted where you work.

Updated 2026-09-30